If you live on the south side of Highland Road, how do you get onto Mequon's newest trail? The answer was settled in 2024, after a long argument over which side of the road the path should go on. Today it decides how every walk, run and ride on the Highland Road Bike Spur begins.
The path is finished. In the News Graphic's report on the opening, organizers, local officials and residents gathered on a Sunday for a ribbon cutting at the South Pavilion in Rotary Park, 4100 W. Highland Road. The spur is a 1.5-mile off-road paved trail that links the Ozaukee Interurban Trail to Rotary Park along the north side of Highland Road. The City of Mequon's weekly bulletin set the celebration for Sunday, October 18, at 4:00 p.m.
The North Side Was the Whole Argument
The MT Trails Foundation spent years on one question before construction began: north side or south side. Its project history lists the reasons the north side won.
- Safety studies. A study in April 2024 found the north side significantly safer on both weekdays and weekends. A second study in July 2024 found it significantly safer on weekends and about the same on weekdays.
- Distance from homes. A south-side trail would have run within 7 feet of neighbors' backyards. The north-side route sits a considerable distance from houses.
- Legal limits. According to the foundation, a trust agreement with Highland Woods keeps the path on the north side from the Interurban Trail to Cedarburg Road, and the city had no right-of-way authority on the south side from Cedarburg Road to the Meadows subdivision.
- Fewer crossings. Switching to the south side between Cedarburg Road and Rotary Park would have forced riders coming from the Interurban Trail to cross Highland twice more.
The News Graphic gave the same reasons. It added that a south-side route would have meant buying more land and delaying the project.
Time was a factor too. On December 10, 2024, WisDOT gave MT Trails until March 25, 2025, to submit an approved final design. Missing that date would have cost the project its $988,000 grant, and the foundation said it could not reapply until 2028, if a new grant was approved at all. About 80 residents attended a public meeting at City Hall on January 23, 2025, where design consultant Kapur Inc. presented the north-side layout.
What the Decision Means for You
The north-side choice shapes the path in three ways you notice right away.
First, the road ditch is the buffer. The foundation's plan puts the trail inside the city's 50-foot right-of-way on the north side, with the drainage ditch between the cars and the path. The path is 10 feet wide and paved with asphalt.
Second, if you live on the north side, your stretch of Highland connects directly to the path. If you live on the south side, you join it at a crossing. The foundation's plan calls for marked, controlled crossings at Green Bay Road and River Road, plus a proposed marked crossing at MATC. River Road got a new flashing crosswalk beacon as part of the project.
Third, the two ends lead to different places. The final plans put the western start near the MATC west entrance, at the Interurban Trail end. The eastern end is Rotary Park. The foundation describes the spur as a way to reach the Interurban Trail and the Mequon-Thiensville Town Center.
Lori Lorenz, of the MT Trails Foundation Board of Directors, spoke to the News Graphic earlier this year, before the opening. "This project will strengthen connections between neighborhoods, parks and existing trail systems while expanding safe and accessible options for people of all ages to walk, bike and enjoy the outdoors," she said.
How It Got Built This Year
Because the route was settled, 2026 went quickly. Here is the order of work, pieced together from the foundation and the city:
- March 9 to 31. Trees and brush in the corridor were cleared within a set window to protect northern long-eared bats. One Bur Oak, previously identified as a specimen tree, was left standing.
- Spring. Construction began with Buteyn-Peterson Construction Company as the contractor and raSmith as project manager.
- Mid-July. Grading began on the trail.
- September. Paving began. The city's September 11 bulletin noted that some families were already using the trail before it was paved.
- October 18. The ribbon cutting took place at the Rotary Park South Pavilion.
The work also added stormwater infrastructure along the route.
What 1.5 Miles Cost
The federal Transportation Alternatives Program grant, administered through WisDOT, covered most of the cost. Community grants and individual donations covered the rest, and Mequon-Thiensville Sunrise Rotary was the first community grantor. These figures come from the foundation's cost table, updated February 25, 2026, and its fundraising count as of August 31, 2026:
| Line item | Amount |
|---|---|
| Design | $219,300 |
| Construction and project management | $970,400 |
| Other costs | $10,300 |
| Total to build the path | $1.2 million |
| Maintenance endowment | $100,000 |
| Total funding need | $1.3 million |
| Raised as of Aug. 31, 2026 | $1.221 million |
Compare the grant to the build cost and you see why the March 2025 deadline mattered. The $988,000 grant equals most of the $1.2 million cost to build. The money raised by the end of August covered the full build cost and part of the endowment.
Rotary Park Sits at the Eastern End
The City of Mequon's Rotary Park page lists fishing ponds, a pavilion with a grill and washrooms, picnic areas, a playground, fields, a walking trail and wooded trails. The city's Parks Division maintains all city parks.
At the western end, the Ozaukee Interurban Trail is meant for year-round use: biking, in-line skating, walking, running and cross-country skiing. Motorized vehicles, snowmobiles included, are not allowed, and neither are horses.
Where the Path Leads in December
The spur's first full month after opening coincides with Thiensville's holiday calendar, and the Interurban Trail connects the two. Downtown Thiensville is marking its 40th anniversary this year. Its business association was founded in 1986, and its executive director, Traci Cain, told the News Graphic that the anniversary would bring "enhanced programming and new elements" to its events.
These are the dates on the Downtown Thiensville calendar and the Village's notices:
- Light Up The Village, Saturday, November 7. This was the string-light installation day along Main Street and Green Bay Avenue and the first item on the village's Christmas calendar.
- Turkey Trot, Thursday, November 26, 9:00 a.m. The Junior Woman's Club runs its 22nd annual race on Thanksgiving morning, according to the Village of Thiensville.
- Christmas Tree Lighting, Friday, December 4, 6 to 7 p.m. Check the event listing for the location before you go.
- Cookie Walk, Saturday, December 5, 10 a.m. to 2 p.m. The walk runs through businesses all over Thiensville. This is its second year, after the first Cookie Walk in 2025.
For a warm stop along the way, Fiddleheads Coffee at 192 S. Main St. describes itself as a bicycle-friendly café on the Milwaukee River along the village's main street. In September it supplied bread, cakes and coffee for Downtown Thiensville's Village Table dinner.
The North Side Could Keep Going East
The north-side choice also leaves room to extend the path. In 2024, the Joint Mequon-Thiensville Bike and Pedestrian Way Commission hired the consulting firm GRAEF to draft a 20-year vision. Its November 2024 draft named all of Highland Road, from Port Washington Road to the Interurban Trail, as a primary recommended east-west bike route, built as an off-road sidepath. North-side paths already exist farther east, off Port Washington Road. Keeping the new spur on the north side lets the two link up someday. For now, the GRAEF route is a planning recommendation, not a scheduled project.
Want to know how far your street is from a Highland Road crossing, or which Mequon homes connect directly to the new path? Kurtin Realty has lived and worked along these roads for years, and we're glad to talk through the trail map with you. When you're ready to see what your home is worth with a paved trail nearby, Kurtin Realty can help. Request your free home valuation.